1.       Project Description

This project studies the present communication channel being used by employers in requesting Unirazak students qualified for employment. The proposed system is aimed at automating and creating a dedicated channel for the student recruitment process. This system is targeted at employers, recruitment agents and the members of staff and students of the faculty of Information technology, Unirazak to assist them in the recruitment process. Employers and recruitment agents can post vacancies and also advertise, lecturers can make recommendations while students can post their resume and apply for vacancies. The system also allows communication amongst employers, recruitment agents, lecturer and students.
 

2.       Business Objectives and Success Criteria

There would be some cash income for the university through the advertisements by different companies. Besides that, it would increase UNIRAZAK’s affiliations all over Malaysia as companies would be able to deal direct with the faculty of IT. To add on, it would increase the student enrolment for IT courses as the employment rate of UNIRAZAK IT student would be high.

3.       Stakeholders

Stakeholder
Major Benefits
Attitudes
Win Conditions
UNIRAZAK staff and management
Able to showcase their best students.
Co-operative and positive
Undergraduates are hired, therefore reduces number of unemployed graduates
Project Manager
Gets experience in managing a system
Requires knowledge and practice in general management ideas
Understanding, navigating and meeting with the stakeholders need and expectation.
Leading, communicating and problem solving with stakeholders.
UNIRAZAK Job Seekers
A convenient medium that aids them in job hunting.
Hopeful and positive in securing a job.
Gets a job.
Employers
A convenient medium that aids them in finding suitable candidate for a job position.
Have high requirements on candidates
Gets a suitable candidate for the job offered

4.       Vision

This system is targeted at employers, recruitment agents and the members of staff and students of the faculty of Information technology, UNIRAZAK to assist them in the recruitment process. The system is known as UNIRAZAK Online Student Recruitment System that is aimed at automating and creating a dedicated channel for the student recruitment process. Employers and recruitment agents can post vacancies and also advertise, lecturers can make recommendations while students can post their resume and apply for vacancies. The system also allows communication amongst employers, recruitment agents, lecturer and students. Unlike the existing system which is totally manual in nature, the employers only informs the university staff of their need of UNIRAZAK student for employment through traditional means like face to face, letters, phone calls, emails and so on. 

5.       Project Scope

Determining the context of the project means defining the specific boundaries, or extent of the project. For the purpose of this project, our task is to develop an Online Student Recruitment System for UNIRAZAK which is an operational system. The system is to facilitate the recruitment process of UNIRAZAK IT students. The end users of the system are the Malaysian employers, Malaysian recruitment agents, UNIRAZAK IT students and the UNIRAZAK faculty of IT, each performing a different duty towards achieving the universities goals and objectives. 


6.       Assumptions and Dependencies

AS-1:
DE-1:

7.       Constraints


Dimension
Constraint
(state limits)
Driver
(state objective)
Degree of Freedom
(state allowable range)
Features


70-80% of high priority features must be included in release 1.0
Quality


90-95% of user acceptance tests must pass for release 1.0, 95-98% for release 1.1
Cost


budget overrun up to 15% acceptable without executive review
Schedule

release 1.0 to be available by 10/1, release 1.1 by 12/1

Staff
maximum team size is 6 developers + 4 testers


7.       Milestones

Event or Deliverable
Target Date
Responsibility
Project charter approved
24 June 2010
Team leader/ Project manager
Project plan completed
-
All members
Project plan approved
14 June 2010
Project manager
Project team assembled
10 June 2010
All members
Project execution initiated
-

Project execution completed
-

Customer acceptance
6 July 2010

Project closed out
11 July 2010
All members

8.       Business Risks


Risk
Probability
Impact
Mitigation
Implementation Issues
  40%
severe

User acceptance
  60%
maximum

Missed deadline
  45%
Minimum

9.       Resources


Resource
Description and Source
Computer system






10. Approvals


Approval Decision:

¨  Approved, development of detailed project plan is authorized
¨  Approved, project execution is authorized
¨  Approved, but project is on hold until future notice
¨  Revise charter and resubmit for approval
¨  Charter and project proposal are rejected

Role or Title
Name and Signature
Date